Example Task: Check for projector lamps close to needing replacement
In this example, a task to check to see if the estimated lamp life remaining for projectors is below a specied num-
ber of hours limit is created. This is recommended in order to perform proactive ordering of replacement lamps
and maintenance. The task will be set to run once every week, and an email will be sent to the administrator if any
projector’s estimated lamp life remaining is less than 100 hours.
1. Create a new Task by clicking the New Task toolbar button, or selecting New Task... from the Tasks
menu.
2. Enter a Name and Description for the task to indicate the purpose of the task.
3. Since the task will check the condition of a value, select the Task Type: Conditional.
4. Since it is only necessary to check each projector once each time the task is run, select Polling Interval
and Total Run Time: Poll one time only.
5. On the Devices tab, select the projectors to be checked.
6. On the Conditions tab, open the Display Device Information section on the Controls list, and select
Est. Lamp Life Remaining to add it to the list of conditions.