8.40
Section 8
Electrical System and Components
Plunger
Pushed “In”
VOM Meter
Leads
12 volt Test Leads
Test 4. Solenoid Hold-In Coil/Contact Continuity
Test.
Use an ohmmeter set to the audible or Rx2K scale, and
connect the two ohmmeter leads to the two large post
terminals. Perform the preceding test (3) and check for
continuity. See Figure 8-77. The meter should indicate
continuity, if no continuity is indicated the solenoid
should be replaced. Repeat test several times to
confirm condition.
Figure 8-77. Testing Hold-In Coil/Solenoid Contact
Continuity.