1.3 Operator Installation
• Position the operator on the pad so that
there is a minimum clearance of one (1)
inch between the back of the operator
housing and the gate.
90°
• IMPORTANT!! Be sure that the operator
is parallel to the gate! Installing the
operator in any other manner will cause
excessive chain noise, chain wear and
stretching, and premature idler failure.
• Mark the mounting holes on the mounting
pad. Use a concrete drill bit to drill the
mounting holes to the size and depth
required for the anchors being used. We
recommend 1/2 x 2 or 3/8 x 2 sleeve
anchors (not supplied).
NO!
• After drilling the mounting holes, clean
them out and install the sleeve anchors.
Position the operator over the anchors
and tighten.
15