STEP 4: INSTALLING THE TRIP ROD GUIDE
A. Align the new Trip Rod Guide with the Trip Rod
and the existing holes in the middle Breaker
Shelf, as shown in Fig. 7.
B. Secure the Trip Rod Guide to the middle
Breaker Shelf using the (2) .190-32 × .500"
screws, (4) flat washers, (2) lock washers, and
(2) nuts supplied.
STEP 5: DRILLING THE BREAKER FOR
MOUNTING THE RETROFIT
COMPONENTS
NOTE: Throughout the drilling process detailed in
this Step, insure that no drill shavings fall
into the Breaker.
A. Using Drilling Plan “A”, drill two (2) .266"
diameter holes in the right Breaker Frame.
These will be used later in the Retrofit Process
to mount the DTA.
Fig. 6 Overview: Trip Rod Guide Installed in the
Breaker
Fig. 7 Installing the Trip Rod Guide
.75
3.5
4.0
DRILL .266 DIA (2)
Fig. 8: Drilling Plan “A”
B. For Kits Supplied with an Auxiliary Switch Only:
Using Drilling Plan “B”, drill two (2) .170"
diameter holes in the front left edges of the top
and middle Breaker Shelves. These will be
used later in the Retrofit Process to mount the
Auxiliary Switch Assembly.