RB 211 Maintenance Scope
B-7
RB 211 - Overhaul Workscope
This overhaul workscope is conducted as schedule maintenance at approximately 50,000
Operating Hours, providing the engine had a midlife inspection repair at 25,000 hours.
On Receipt of Engine
Take pictures of engine on the inbound truck (i.e. tie down straps etc.)
Inspect and report condition of engine transportation stand and bag.
Open bag and photograph all four sides of the engine especially engine components or parts
that are damaged or missing.
Carry out full “booking in” inspection of the engine, checking that the rotating assemblies are
free of rubs and stiffness.
Any missing parts/components or other visual abnormalities should be immediately reported
to the Customer.
Remove the Nose Bullet, “A” Frame, Intake Extension Ring etc. and prepare the engine for a
vertical lift.
Carry out an airflow check of the 01, 03 and 05 module oil lines and record findings.
Place the engine on the “pot” vertically for removal of all the 06 module components
(i.e. all pipes, harnesses etc.)
Bulk strip the engine into its five (5) modules.
01 Module:
Air Inlet and Front Bearing Support (Section 1020)
Detail strip the module – wash, NDT and inspect all components.
Replace the I.P. Roller Bearing.
Incorporate MOD 633 on IP front static seal.
Inspect anti-icing manifold, check for damage, cracks or other defects. Ensure MOD 961 is
embodied.
Inspect anti-icing sleeve for wear. NOTE: Discuss with Customer deletion of Anti-Ice
System (Mod 1051) where applicable.
Inspect nose bullet for dents, cracks and other defects. Incorporate IRBT1120.
Inspect support frame assembly. Incorporate IRBT1120.
Inspect actuating ring check for free movement.
Inspect bearing, housing, repaint if necessary.