14
Installation
Doc 01-G0610
Rev A
Pedestal Mount Installation
1 Locate pedestal according to Figure 8. Locate
the electrical conduit. Wires may be run inside
pedestal and through holes in the bottom of
chassis.
Operator cabinet may be installed either
parallel or perpendicular to the fence.
2 Excavate required areas for pedestal and
conduit. Pedestal should be below the frost line
or as required by local codes.
Pedestal should protrude no more than 12”
above ground.
3 Bolt the mounting brackets to the pedestal as
shown in Figure 8.
4 Set pedestal and electrical conduit in place.
IMPORTANT NOTE: The relative location
of the operator to the fence and the gate is
critical. Be sure that the measurements for
operator mounting are taken from the
centerline of the fence and of the gate
hinge.
5 Pour cement to secure pedestal in place. Allow concrete to set for (2) days before
installing power unit.
6 After concrete has set, secure the operator to
the pedestal by dropping it onto the pedestal and
allowing the mounting studs to slip through the
holes on the pedestal brackets.
Secure with hex nuts provided. It is
important that the operator be level.
SW420 PEDESTAL
PARALLEL MOUNT
GATE
PIVOT
HINGE PIN
FENCE LINE
GATE
SW420 PEDESTAL
PERPENDICULAR MOUNT
PEDESTAL 24” DEEP
IN-GROUND MINIMUM
PIVOT
HINGE PIN
FENCE LINE
NUT TYP. (8X)
BOLT TYP. (4X) FROM
BRACKET TO PEDESTAL
01-G0610F8
Figure 8