Periodic maintenance and adjustment
90
9. Tighten the V-belt position adjusting
bolts.
10. Install the V-belt over the primary sheave
assembly.
11. Rotate the secondary sliding sheave
clockwise and push it so that it separates
from the secondary fixed sheave.
12. Install the V-belt between the secondary
sliding and fixed sheaves.
13. Place the left lower cover in the original
position, and then install the screws
(RS90GT / RS90LTGT / RST90GT).
1. V-belt position adjusting bolt
2. Spacer
V-belt position Adjustment
More than 1.5 mm
(0.06 in) above the
edge
Remove a spacer.
From 1.5 mm (0.06 in)
above the edge to 0.5
mm (0.02 in) below
the edge
Not necessary (it is
correct).
More than 0.5 mm
(0.02 in) below the
edge
Add a spacer.
V-belt position adjusting bolt tightening
torque:
10 Nm (1.0 m·kgf, 7.2 ft·lbf)
1. Secondary sliding sheave
2. Secondary fixed sheave
1. V-belt
U8JA11E0.book Page 90 Monday, June 14, 2010 10:22 AM