NorthStar Navigation 10 kW Radar Detector User Manual


 
Repeat this for procedure for each bolt, then tighten all the nuts so that the scanner is secure.
NOTE: Use the bolts supplied as these are hardened stainless steel and the correct length.
3.3.8 When to install the open array
IMPORTANT: Install the open array onto the scanner AFTER you have connected the interconnection
cable to the scanner otherwise you'll have to remove the open array from the scanner, and then re-
install it.
3.3.9 Install the radar processor
Install the radar processor in a dry location away from spray, rain, drips, and condensation.
The location site must allow you to easily connect the radar processor to the ship's ground, the
interconnection cable, the power cable, and the 6000i and 6100i radar communications cable or the
8000i network cable. Check that these cables and the ship's ground can easily reach the radar
processor BEFORE you drill.
The radar processor dimensions are shown on the drilling template. Follow the instructions on the
drilling template to install the radar processor.
Northstar 10 kW Radar Installation Manual
19