4.2.3 Precautions in transportation
To prevent the device from being damaged during transportation, the original packing should be left
untouched until the device arrives near the intended installation site.
The detector is equipped with hanging hooks. Lift it as shown in Figure 4.5. For information on the
actual mass of each diameter, refer to Table 4.2.
* The lifting work should be executed by those qualified for crane work or slinging work
Figure 4.6 Transportation of GF63* flowmeter detector
CAUTION
(1)Never lift the detector by inserting a bar
into its measurement pipe, because this will
damage the linings, thus making it impossible
to take stable measurements.
(2)To put the flowmeter temporarily on the floor,
place it carefully with something, such as
stopper, to support it so that GF630/LF600F,
GF630/LF610F and GF632 will not topple over.
Wire or cloth belt
is used.
Cloth belts
should only can be
used
because wire may cause damage to
the detector or converter body.
(a) Meter size 200mm to 600mm (8" to 24")
Hanging hooks are provided
(b) Meter size 15mm to 150mm (1/2" to 6")
Hanging hooks are not provided
Stopper, etc. to prevent from toppling over it.
flowmeter
90°or less
Lifting Lugs
flowmeter
A bar, etc. to lift
the flowmeter.