Garmin GTP 59 GPS Receiver User Manual


 
Page 8-2 G3X Installation Manual – Post Installation Checkout and Calibration Procedures
Revision A 190-01115-01
8.1 Recommended Test Equipment
The following test equipment is recommended to conduct and complete all post installation
checkout procedures in this section: (All test equipment should have current calibration
records)
Pitot/static ramp tester
Digital Multi-Meter (DMM)
Ground power unit capable of supplying 14/28 Vdc power to the aircraft systems and avionics
Outdoor line-of-site to GPS satellite signals or GPS indoor repeater
Digital Level or equivalent
8.2 GDU 37X Test Procedure
Test the GPS Receiver:
1. Power on unit and use the FMS Joystick to select the Info Page.
2. Verify that the GPS receiver is functional and able to calculate its present position.